Construction of a 12-million-gallon manure storage lagoon including 68,000 cubic yards of topsoil and on-site cuts and fills, Installation of 3,800lf of 8” DR11 for the transmission line, 60mil HDPE Liner installation, and concrete agitator pads.
Some key aspects of the project include a 600' foot access road, stripping over 9,000 cubic yards of topsoil, moving over 45,000 cubic yards of material for onsite cuts and fills, installing 60mil plastic liner and installation of 3,800 lf of 8" transmission line from the farm.